The 'Mechanic's Lien' in Ontario: It's a Construction Lien — Here's the Process
Searching for the mechanic's lien process in Ontario? The correct Ontario term is construction lien under the Construction Act. The process, the deadlines and the terminology, explained.
Reviewed by Ayoun Haroon, Partner, Ayoun & Sabeeya LLP
Published August 31, 2026
First, the terminology — Ontario says construction lien
"Mechanic's lien" is the older term still used in much of the United States and in older Canadian materials. Ontario retired it decades ago: the modern statute is the Construction Act, and the remedy is the construction lien. If you are reading American guides about notarized lien affidavits and county recorders, put them down — none of that procedure applies here.
The good news: what you are trying to do — secure payment for work or materials against the property you improved — works in Ontario, and arguably with more structure, through preservation, perfection, holdback and prompt payment.
The Ontario process at a glance
- Supply work or materials that improve the premises — this creates the lien right
- Preserve the lien, generally within 60 days of your trigger date, by registering a claim for lien on title
- Perfect the lien within the following 90-day window by starting a Superior Court action (and registering a certificate of action where required)
- Look to the 10% statutory holdback each payer must retain
- Consider prompt-payment notices and ODACC adjudication for a faster interim decision
Where imported (US) assumptions break Ontario claims
Three imported mistakes appear constantly: waiting for a "notice of completion" that Ontario does not use the same way; assuming a one-year filing window when Ontario's preservation period is measured in days; and sending a US-style "preliminary notice" instead of registering a claim for lien. Every one of these can cost the entire lien right.
If your project, contract or dispute has any complexity — multiple payers, terminated contracts, disputed last-supply dates — get Ontario advice on your actual trigger dates rather than guessing.
Talk through your dates before they expire
Bring the contract, the invoices and a timeline to a consultation. The first 15 minutes are free, we confirm the deadlines that apply to your role in the chain, and defined steps like preserving the lien are quoted flat.
The content of this website is legal information about Ontario and Canadian law, not legal advice. Reading it, or contacting us through it, does not create a lawyer-client relationship — that begins only after we confirm in writing that the firm is acting for you.