Ontario's Construction Act Liens: Key Questions Answered

How construction liens work under Ontario's Construction Act: who can lien, the 60-day preservation and 90-day perfection deadlines, holdback, and what owners should do when a lien lands on title.

Ayoun Haroon

Reviewed by Ayoun Haroon, Partner, Ayoun & Sabeeya LLP

Published April 2, 2025 · Updated August 31, 2026

The content of this website is legal information about Ontario and Canadian law, not legal advice. Reading it, or contacting us through it, does not create a lawyer-client relationship — that begins only after we confirm in writing that the firm is acting for you.

Questions people also ask

Can a lien be registered after the 60 days?+

No — the preservation deadline is strict. A lien registered late is invalid and can be discharged, though the underlying debt claim may still proceed as a normal lawsuit.

Does a lien mean the owner has to pay twice?+

Properly retained holdback is the owner's protection: liability to subcontractor lien claimants is generally limited to the holdback the owner should have retained. Owners who skipped holdback lose that protection.

We were never paid — is a lien our only option?+

No. Ontario's prompt payment and adjudication regime provides a fast interim process for payment disputes, and an ordinary contract action remains available. The right tool depends on your timeline and where you sit in the construction pyramid.